Structural and Civil Engineers
Land and Building Surveyors
TYPICAL RECENT PROJECTS

LYDIARD FIELDS, SWINDON
CLIENT
The Equitable Life Assurance Society

Employed as civil and structural engineering consultants on a 50 acre development of greenfield site for mixed use, i.e. leisure, warehousing and offices adjacent to M4 Junction 16 at Swindon. £4.5 million enabling works contract for initial infrastructure involved the moving of 650,000 cubic metres of Kimmeridge Clay to form landscaped mounds, the construction of a highway network including roundabouts, foul and surface water drainage installations including a major balancing pond to attenuate surface water flows and an underground pumping station. Subsequently SDP was retained as engineering consultants on two speculative warehouse schemes totalling 100,000 sq.ft and a £10 million 300,000 sq.ft distribution warehouse for Sainsburys Homebase. SDP have a continuing involvement in the site which has planning for a further 300,000 ft2 of offices.

SALTASH DEVELOPMENT, LAMBETH
CLIENT
Laing Partnership Housing

Employed as civil and structural engineering consultants on a £5 million inner city regeneration project to replace an existing concrete framed high rise development including underground car parking with two to three storey housing. The scheme required new piled foundations carefully designed and located to avoid existing piles and SDP was also employed to accurately locate the existing piles and provide dimensional management during construction.

MARITIME QUAY, ISLE OF DOGS
CLIENT
Redrow Homes (South East) Ltd

Employed as civil and structural engineering consultants on a £12 million mixed housing development ranging from two/three storey housing to six storey flats along the river frontage. The initial site appraisal indicated poor ground conditions, a high water table and major underground obstructions, some of which dated back to the mid 19th century and included the foundations of Brunel’s Great Eastern slipway. The site was also contaminated. The ground conditions necessitated piled foundations and SDP proposed that each pile position should be probed prior to installation and moved if necessary and appropriate to avoid obstructions. Those piles which could not be moved were augured through with a purpose-made cutting head. The six storey flats on the river frontage were originally proposed to be constructed in load bearing masonry with transfer structures at first and fourth floor level but due to anticipated problems with bricklaying sub contractors, the final scheme was designed as a reinforced concrete frame with a transfer structure at first floor above the basement car park. The location of the piles to the flats along the river frontage were further compounded by the existing river wall ties.